top of page

Pier 94 Backlands

Client: Port of San Francisco

Contractor: Fontenoy Engineering 

Project Value: $1.3M

Project Overview:

This project involved the construction of a reinforced concrete headwall and associated stormwater infrastructure improvements for a newly installed 36-inch storm drain outfall at Pier 94 and serves a 15-acre redeveloped industrial zone, improving stormwater management and environmental compliance.

To facilitate the concrete wall structure, a cofferdam was constructed preventing tidal waters from entering the construction zone.

In addition to installing the 36'' storm drain by open-cut methods, slip lining was performed under an existing concrete plant.​

Strategic Approach:

  • Headwall Construction:

    • Built 15 feet below high tide, requiring a sheet pile cofferdam and 24/7 dewatering.

    • Work was tidal-dependent, limiting hours.

  • Slip Lining an Existing Pipe:

    • Reinforced 250’ CMP pipe under Amador St. and Central Concrete plant.

    • Managed collapsed sections due to heavy truck/equipment loads.

    • Coordinated closely with Central Concrete to avoid disruptions.

  • Additional Work:

    • Installed three large cast-in-place manholes for pipe transitions.

Fontenoy Engineering Logo

Tel: 415 740-0268

Fax: 415 852-5472

Fontenoy Engineering,
3450 3rd Street, Unit 4D,
San Francisco,
CA 94124

©2025 Fontenoy Engineering Inc. All Rights Reserved.

bottom of page